example 1
node diagram 1
gantt chart 1
example 2
node diagram 2
gantt chart 2
example 3
node diagram 3
gantt chart 3
example 4
1) Draw a correctly labelled diagram that includes all tasks in the table
2) Calculate the minimum amount of time required to complete the project.
2) Calculate the minimum amount of time required to complete the project.
node diagram 4
The critical path is A-B-D-G-H and the minimum time to complete the project is 19 days.
gantt chart 4
Calculate the minimum number of line supervisors needed for the project (one supervisor per line)
Move the critical path into the top line of the chart.
Move the critical path into the top line of the chart.